Sprint 19
Download CSV
January 16 - 29
Off-track by 33%
Story Points
Complete
14
Remain
7
Total
21
Issues and Pull Requests Issues and PRs
Complete
5
Remain
2
Total
7
Remaining Issues or pull requests Remaining Issues or PRs
Assignees / Points
-
va.gov-team #98595
Added
🏃♀️ Upcoming Sprint
lindsay-insco
-
va.gov-team-sensitive #2184
Added
🏃♀️ Upcoming Sprint
jwoodman5little-oddballalyssagallionbdech
Completed Issues or pull requests Completed Issues or PRs
Assignees / Points
-
va.gov-team #83656
Added
✅ Done
bdech
-
va.gov-team #97706
Added
✅ Done
lindsay-inscodavidpetras
-
va.gov-team #95713
Added
✅ Done
lindsay-inscoGWright321
-
va.gov-team #101740
Added
✅ Done
davidpetras
-
va.gov-team #101850
Added
✅ Done
bdech